Accord DEA Guidelines for Garments Building in Bagladesh


1. AS-BUILT DRAWINGS:
As-built drawing should be generated in order to concisely record the general arrangement of the
building and size and location of the structural elements.
As-built structural drawing set should include:
a. Foundation layout.
b. Ground floor layout.
c. First floor layout.
d. Additional floor layouts for each additional suspended floor or mezzanine including beam
and column schedule and existing super- imposed dead loading.
e. Roof layout.
f. Building elevations.
g. Building sections.
h. CAD Softcopy of As-built should be submitted along with DEA.
i. Scan Report of structural members with As built Structural Drawings.
2. ENGINEERING TESTS:
a. Geotechnical investigation (If Required)
Sufficient on site opening up to be carried out to test or investigate the foundation system, bearing
levels, bearing capacities and condition of the representative sample of elements below ground for size,
corrosion and condition.
Saturday, October 7, 2017
Accord Advised Fire EXTINGUISHER MAINTENANCE INSPECTION CHECKLIST

Accord Advised Format for Fire EXTINGUISHER MAINTENANCE INSPECTION CHECKLIST.
Note: To be completed by the Inspector at the time of Inspection Attach additional sheets, data or calculation as necessary to provide a complete record.
Accord FIRE ALARM AND DETECTION SYSTEM INSTALLATION INSPECTION CHECK LIST

Accord Advice Format for FIRE ALARM AND DETECTION SYSTEM INSTALLATION INSPECTION CHECK LIST.
To be completed by the Inspector at the time of Inspection Attach additional sheets, data or calculation as necessary to provide a complete record.